Construction Projects
-
Lakeville Area Schools has several construction projects that will benefit our students, staff and community. These projects are being built using 2019 bond referendum dollars and school board-approved lease levy dollars. Please find information on our many exciting projects below.
Details of these projects will be updated throughout the design and construction process.
Current Projects
-
Highview Elementary School
Summary
A new elementary school is coming to Lakeville Area Schools. Officially named Highview Elementary, it will be the district's ninth elementary school. The school was approved by voters in the May 11, 2021 bond referendum to address growing enrollment in the district.
The site for Highview Elementary is 35 acres of land located at 18601 Highview Avenue in Lakeville. The location on Highview Avenue was picked based on its road access, utilities infrastructure locations, and the size of the property. The location is just east of King Park, east of Century Middle School and south of Cherry View Elementary. There are newer neighborhoods close to the site, including some that are still being built and some that are planned to be built in the future.
Construction began in Summer 2022 with a targeted opening date of Fall 2024.
Keep checking back on this page for more information as the project develops.
School Features
- 100,000 square foot building
- Five sections of K-1 graders
- Four sections of 2-5 graders
- Four center-based special education classrooms
- Specialists to include Music, STEM, Gym and Art
Design & Construction Team
Funding Source
Bond Referendum
April Construction Tour featured in Everything to Know in 194 Admin Update
Construction Updates from Loeffler Construction
Episode 1
Episode 2
Episode 3
Episode 4
Episode 5
Episode 6
Episode 7
Episode 8
-
Dome Ready Practice Turf
Summary
Addition of two dome ready practice turf fields--one at Lakeville North High School and one at Lakeville South High School.
Design & Construction Team
Timeline
Practice turfs completed Summer 2021
Funding Source for Dome Ready Practice Turf Fields
2019 Bond
Questions and Reservations
For questions and reserving practice turfs between May through mid-October, exact dates will vary at both Lakeville North High School and Lakeville South High School please contact the District’s Facility Use office at facilitiesuse@isd194.org or by calling 952-232-2155.
Questions About TCO Dome at Lakeville North
On April 27, 2021 the School Board approved an agreement with Dome Partners LLC to put up a dome Lakeville North’s dome-ready practice turf for 6 months of the year. For questions regarding operations and scheduling space at the TCO Dome at Lakeville North, please visit their website: tcodomelakeville.com
-
Eastview Elementary Addition
Summary
Addition of 4 new classrooms, small and medium group rooms, learning commons and additional restrooms on two levels.
Design & Construction Team
Timeline
Anticipated completion of 1st day of school in Fall 2021
Funding Source
Lease Levy
Gallery
Construction of the Eastview addition as of March 15, 2021
-
John F. Kennedy Elementary Addition
Summary
Addition of 4 new classrooms, small and medium group rooms, learning commons and additional restrooms on one level.
Design & Construction Team
Timeline
Anticipated completion of 1st day of school in Fall 2021
Funding Source
Lease Levy
Gallery
Construction on the John F. Kennedy addition as of March 15, 2021
-
Christina Huddleston Elementary Addition
Summary
Addition of 4 new classrooms, medium group rooms, learning commons and additional restrooms on one level.
Design & Construction Team
Timeline
Anticipated completion of 1st day of school in Fall 2021
Funding Source
Lease Levy
Gallery
Construction on the Christina Huddleston Elementary addition as of February 22, 2021
-
Christina Huddleston Parking Lot
Summary
Complete reconstruction of the entire parking lot, bus loop and asphalt playground area, which includes new LED parking lot lighting.
Design & Construction Team
Timeline
Anticipated completion of 1st day of school in Fall 2021
Funding Source
Long Term Facilities Maintenance
-
Century Middle School Parking Lot
Summary
Complete reconstruction of the southern parking lot, which includes new LED parking lot lighting.
Design & Construction Team
Timeline
Anticipated completion of 1st day of school in Fall 2021
Funding Source
Long Term Facilities Maintenance
-
Century Middle School Pool
Summary
Competition and teaching pool addition for swimming, diving and phy. ed. classes.
Design and Construction Team
Timeline
Completed in April 2022.
Funding Source
Bond Referendum
Gallery
Construction progress picture taken November 9, 2021.
A view of the bleachers inside the pool structure on March 22, 2021
Construction of the pool at Century Middle School as of March 15, 2021
The Lakeville Area Schools Blanchard Aquatic Center was completed in April 2022. The following photos of the completed pool and facility space were taken on April 19, 2022.
-
IT Upgrades and Relocation
Summary
- Relocating water pipes in Network Operations Center at Lakeville North High School
- Implementing secondary Network Operations Center for disaster recovery
- Network and wireless infrastructure upgrades
- Network cabling replacement
Design & Construction Team
Timeline
Water Pipe Replacement at Network Operations Center
Design: Winter '20 - Spring '20
Construction: Summer '20Secondary Network Operations Center
Installation: Winter '20 - Summer '21Network and Wireless Infrastructure Upgrades
Summer '20 - Summer '21Network Cabling Replacement
Design: Summer '20 - Fall '20
Construction: Projected to begin Summer '21
Funding Source
Bond Referendum
-
Security
Summary
All school buildings are receiving layered and integrated security system upgrades to minimize the impact of a threat. This includes:
- Classroom lockdown buttons
- Ballistic paneling and window film
- Line-of-sight visibility and access control upgrades
- Perimeter security and detection technology
- Vaping detection at middle and high schools
Design & Construction Team
Timeline
Design: Winter '20 - Spring '20
Construction:
- Vaping detection installation in Summer '20
- Remaining upgrades to be implemented in two phases:
Summer '20 - Fall '20
- Lakeville North High School
- Kenwood Trail Middle School
- Cherry View Elementary (upgrades in half of school)
- Eastview Elementary
- Lake Marion Elementary
- Lakeview Elementary
- Impact Academy at Orchard Lake
Summer '21 - Fall '21
- Lakeville South High School
- Century Middle School
- McGuire Middle School
- Cherry View Elementary (upgrades in remaining half of school)
- Christina Huddleston Elementary
- Crystal Lake Education Center
- John F. Kennedy Elementary
- Oak Hills Elementary
Funding Source
Bond Referendum
Summer 2022 Projects
-
Our Facilities and Plant Planning department, working with our construction partners, made a lot of improvements in our schools and facilities over the summer. Here is a series of before and after photos highlighting the renovation and construction improvements made at our buildings over summer 2022.